Hill of Tillymorgan (Kirkton Farm) Wind turbines

3 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines3
Installed capacity9.6 MW
Turbine capacity3.2 MW
Tip heightnot recorded
Operator (or applicant)LocoGen/ Green Cat Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted March 2011 Permission granted April 2013 Under construction July 2015 Operational December 2016

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3911.

What the register tells us

The application was determined in about 25 months. Construction to first power took about 17 months. The scheme has been operating for about 10 years. That works out at 3.2 MW per turbine on average.