3 turbines · operational · Grampian
| Status | Operational |
|---|---|
| County / region | Grampian |
| Turbines | 3 |
| Installed capacity | 5 MW |
| Turbine capacity | 1.67 MW |
| Tip height | not recorded |
| Operator (or applicant) | Green Cat Renewables |
| Turbine manufacturer | Enercon |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 2 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2923.
The application was determined in about 13 months. Construction to first power took about 14 months. The scheme has been operating for about 16 years. That works out at 1.67 MW per turbine on average.