House O'Hill

3 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines3
Installed capacity5 MW
Turbine capacity1.67 MW
Tip heightnot recorded
Operator (or applicant)Green Cat Renewables
Turbine manufacturerEnercon
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2007 2008 2009 2010 2011 Project timeline Application submitted May 2008 Permission granted June 2009 Under construction August 2009 Operational October 2010

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2923.

What the register tells us

The application was determined in about 13 months. Construction to first power took about 14 months. The scheme has been operating for about 16 years. That works out at 1.67 MW per turbine on average.