🌬️ Onshore wind farm

Howpark Wind Farm
Scottish Borders

Recorded in WhichWindTurbine: 8 wind turbines in operation. Point the app at one of them to see its profile in real time.

8
turbines
16 MW
MW total
2 MW
per turbine
100 m
tip height

📍 8 turbines mapped — each dot is a turbine recorded in the database. Average position: 55.90075 N · 2.28233 W.

Howpark Wind Farm

8 turbines · operational · Scottish Borders

Wind farm facts

StatusOperational
County / regionScottish Borders
Turbines8
Installed capacity16 MW
Turbine capacity2 MW
Tip height100 m
Operator (or applicant)Eurowind (UK) Limited
Turbine manufacturerVestas
Turbine modelV80
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~204620182020202220242026today123456
  1. 1Aug 2016 — Application submitted
  2. 2Apr 2017 — Refused
  3. 3Apr 2018 — Permission granted
  4. 4Apr 2018 — Granted on appeal
  5. 5Mar 2021 — Under construction
  6. 6Jan 2024 — Operational

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6214.

What the register tells us

The application was determined in about 20 months. Construction to first power took about 34 months. The register records a refusal in April 2017 before the scheme progressed. Permission was ultimately granted on appeal in April 2018. The scheme has been operating for about 2 years. That works out at 2 MW per turbine on average.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.