8 turbines · operational · Scottish Borders
| Status | Operational |
|---|---|
| County / region | Scottish Borders |
| Turbines | 8 |
| Installed capacity | 16 MW |
| Turbine capacity | 2 MW |
| Tip height | 100 m |
| Operator (or applicant) | Eurowind (UK) Limited |
| Turbine manufacturer | Vestas |
| Turbine model | V80 |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 8 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6214.
The application was determined in about 20 months. Construction to first power took about 34 months. The register records a refusal in April 2017 before the scheme progressed. Permission was ultimately granted on appeal in April 2018. The scheme has been operating for about 2 years. That works out at 2 MW per turbine on average.