Hunter's Hill

8 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines8
Installed capacity20 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Wind Farm Developments / RES UK & Ireland
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 Project timeline Application submitted February 2005 Permission granted December 2008 Under construction December 2008 Operational September 2010

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3253.

What the register tells us

The application was determined in about 46 months. Construction to first power took about 21 months. The scheme has been operating for about 16 years. That works out at 2.5 MW per turbine on average.

Nearby

See all wind farms in Co. Tyrone.