🌬️ Onshore wind farm

HydroGlen Project - Glensaugh Farm
Aberdeenshire

Recorded in WhichWindTurbine: 1 wind turbine. Point the app at one of them to see its profile in real time.

1
turbines
1 MW
MW total
1 MW
per turbine
76 m
tip height

📍 1 turbine mapped — each dot is a turbine recorded in the database. Average position: 56.85441 N · 2.51592 W.

HydroGlen Project - Glensaugh Farm

1 turbines · under construction · Aberdeenshire

Wind farm facts

StatusUnder Construction
County / regionAberdeenshire
Turbines1
Installed capacity1 MW
Turbine capacity1 MW
Tip height76 m
Operator (or applicant)The James Hutton Institute
Turbine manufacturernot recorded
Turbine modelnot recorded
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2024202520262027today123
  1. 1Feb 2024 — Application submitted
  2. 2Apr 2024 — Permission granted
  3. 3Jan 2025 — Under construction

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 15874.

What the register tells us

The application was determined in about 2 months. That works out at 1 MW per turbine on average.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.