Inishative

6 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines6
Installed capacity13.8 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Gaelectric Developments/ CGN Europe Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted November 2006 Permission granted November 2010 Under construction February 2015 Permission expired November 2015 Operational March 2017

From application to operation, this scheme took about 11 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4245.

What the register tells us

The application was determined in about 48 months. Construction to first power took about 25 months. A planning permission on this site expired in November 2015. The scheme has been operating for about 9 years. That works out at 2.3 MW per turbine on average.