Jack's Lane Wind Farm

6 turbines · operational · Norfolk

Wind farm facts

StatusOperational
County / regionNorfolk
Turbines6
Installed capacity13.8 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Aviva
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted August 2010 Refused August 2011 Permission granted May 2012 Granted on appeal May 2012 Under construction July 2014 Operational April 2015 Permission expired May 2017

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4649.

What the register tells us

The application was determined in about 21 months. Construction to first power took about 9 months. The register records a refusal in August 2011 before the scheme progressed. Permission was ultimately granted on appeal in May 2012. A planning permission on this site expired in May 2017. The scheme has been operating for about 11 years. That works out at 2.3 MW per turbine on average.

Nearby

See all wind farms in Norfolk.