19 turbines · operational · Highland
| Status | Operational |
|---|---|
| County / region | Highland |
| Turbines | 19 |
| Installed capacity | 47.5 MW |
| Turbine capacity | 2.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | Renewable Development Company (RDC) |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3202.
The application was determined in about 31 months. Construction to first power took about 9 months. The scheme has been operating for about 18 years. That works out at 2.5 MW per turbine on average.
See all wind farms in Highland.