Kilbraur Windfarm

19 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines19
Installed capacity47.5 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Renewable Development Company (RDC)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2002 2003 2004 2005 2006 2007 2008 2009 Project timeline Application submitted September 2003 Permission granted April 2006 Under construction September 2007 Operational June 2008

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3202.

What the register tells us

The application was determined in about 31 months. Construction to first power took about 9 months. The scheme has been operating for about 18 years. That works out at 2.5 MW per turbine on average.

Nearby

See all wind farms in Highland.