Kilbraur Windfarm Farlary - Extension

8 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines8
Installed capacity20 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Falck Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 Project timeline Application submitted March 2009 Permission granted December 2009 Under construction December 2010 Operational September 2011 Permission expired December 2012

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2673.

What the register tells us

The application was determined in about 9 months. Construction to first power took about 9 months. A planning permission on this site expired in December 2012. The scheme has been operating for about 15 years. That works out at 2.5 MW per turbine on average.