Kiln Pit Hill Windfarm

6 turbines · operational · Northumberland

Wind farm facts

StatusOperational
County / regionNorthumberland
Turbines6
Installed capacity12 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Npower Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted February 2006 Permission granted January 2009 Under construction November 2011 Operational August 2012 Permission expired January 2015

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3938.

What the register tells us

The application was determined in about 35 months. Construction to first power took about 9 months. A planning permission on this site expired in January 2015. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.

Nearby

See all wind farms in Northumberland.