2 turbines · operational · Borders
| Status | Operational |
|---|---|
| County / region | Borders |
| Turbines | 2 |
| Installed capacity | 5 MW |
| Turbine capacity | 2.5 MW |
| Tip height | not recorded |
| Operator (or applicant) | Airvolution Energy |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
The register links a second scheme on this site (REPD ref 4126, Revised): 2 turbines · 2.5 MW each · applicant Wind Direct. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4601.
The application was determined in about 13 months. Construction to first power took about 32 months. The register records a refusal in October 2012 before the scheme progressed. Permission was ultimately granted on appeal in March 2013. A planning permission on this site expired in March 2010. The scheme has been operating for about 9 years. That works out at 2.5 MW per turbine on average.
See all wind farms in Borders.