Kingspan

2 turbines · operational · Flintshire

Wind farm facts

StatusOperational
County / regionFlintshire
Turbines2
Installed capacity1.8 MW
Turbine capacity0.9 MW
Tip height78 m
Operator (or applicant)Kingspan
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2013 2014 2015 2016 2017 2018 2019 2020 Project timeline Application submitted November 2014 Permission granted April 2015 Under construction March 2018 Permission expired April 2018 Operational January 2019

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4790.

What the register tells us

The application was determined in about 5 months. Construction to first power took about 10 months. A planning permission on this site expired in April 2018. The scheme has been operating for about 7 years. That works out at 0.9 MW per turbine on average.