2 turbines · operational · Flintshire
| Status | Operational |
|---|---|
| County / region | Flintshire |
| Turbines | 2 |
| Installed capacity | 1.8 MW |
| Turbine capacity | 0.9 MW |
| Tip height | 78 m |
| Operator (or applicant) | Kingspan |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4790.
The application was determined in about 5 months. Construction to first power took about 10 months. A planning permission on this site expired in April 2018. The scheme has been operating for about 7 years. That works out at 0.9 MW per turbine on average.