8 turbines · operational · Ayrshire
| Status | Operational |
|---|---|
| County / region | Ayrshire |
| Turbines | 8 |
| Installed capacity | 18.8 MW |
| Turbine capacity | 2.35 MW |
| Tip height | 110 m |
| Operator (or applicant) | Corolis Energy/ ESB / Ripple Energy |
| Turbine manufacturer | Enercon |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 9 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4988.
The application was determined in about 25 months. Construction to first power took about 20 months. The register records a refusal in March 2016 before the scheme progressed. Permission was ultimately granted on appeal in February 2017. The scheme has been operating for about 2 years. That works out at 2.35 MW per turbine on average.