3 turbines · operational · Northumberland
| Status | Operational |
|---|---|
| County / region | Northumberland |
| Turbines | 3 |
| Installed capacity | 1.8 MW |
| Turbine capacity | 0.6 MW |
| Tip height | not recorded |
| Operator (or applicant) | Border Wind Farms Ltd /AMEC |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 3 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2587.
The application was determined in about 14 months. The register records a refusal in January 1999 before the scheme progressed. Permission was ultimately granted on appeal in January 1999. The scheme has been operating for about 26 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.6 MW per turbine on average.