🌬️ Onshore wind farm

Knabs Ridge Windfarm
North Yorkshire

Recorded in WhichWindTurbine: 8 wind turbines in operation. Point the app at one of them to see its profile in real time.

8
turbines
16 MW
MW total
2 MW
per turbine

📍 8 turbines mapped — each dot is a turbine recorded in the database. Average position: 53.99806 N · 1.64863 W.

Knabs Ridge Windfarm

8 turbines · operational · North Yorkshire

Wind farm facts

StatusOperational
County / regionNorth Yorkshire
Turbines8
Installed capacity16 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)RWE npower
Turbine manufacturerREpower (now Senvion) (secondary source)
Turbine modelMM70 (secondary source)
Open this wind farm in WhichWindTurbine Interactive map + augmented-reality identification on site

○ Cross-checked reference — turbine make and model (secondary source)

REpower (now Senvion) · MM70 · 8 turbines · 2 MW each

Source: Wikipedia, list of onshore wind farms in England (compiled from RenewableUK's UKWED and The Wind Power), read on 2026-09-19. This is a compiled list, not a primary record. It is shown because two independent facts — turbine count and rated power — match the database exactly. Awaiting confirmation from a primary source.

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

→ ~203020052010201520202025today1234
  1. 1Apr 2004 — Application submitted
  2. 2Nov 2004 — Permission granted
  3. 3Mar 2007 — Under construction
  4. 4Apr 2008 — Operational

The register also records a planning permission expiry in Nov 2013, after construction had started: an administrative date with no effect on the wind farm, left off the axis.

DevelopmentConstructionOperationAhead (repowering horizon at 22 years)

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3147.

What the register tells us

The application was determined in about 7 months. Construction to first power took about 13 months. A planning permission on this site expired in November 2013. The scheme has been operating for about 18 years. That works out at 2 MW per turbine on average.

Sources and dates

DataSourceExtract
Site, capacity, status, planning milestonesRenewable Energy Planning Database (DESNZ, Open Government Licence v3)Q2 2026, published 03/08/2026
Turbine positionsOpenStreetMap contributors (ODbL)19/08/2026
Manufacturer and modelOpenStreetMap tags, unverified — REPD does not record turbine models. Known for 41 % of UK turbines (manufacturer) and 32 % (model); some values are propagated within a site and may be wrong.19/08/2026

Public data may lag behind operator figures. Spotted an error? Suggest a correction from the app.