LADEHEAD FARM - WIND TURBINES

3 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines3
Installed capacity2.4 MW
Turbine capacity1.3 MW
Tip heightnot recorded
Operator (or applicant)PI Renewables 2 Ltd
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted October 2012 Permission granted January 2015 Under construction June 2016 Operational September 2016 Permission expired January 2018

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3915.

What the register tells us

The application was determined in about 27 months. Construction to first power took about 3 months. A planning permission on this site expired in January 2018. The scheme has been operating for about 10 years. That works out at 0.8 MW per turbine on average.