Lambrigg Wind Farm

5 turbines · operational · Cumbria

Wind farm facts

StatusOperational
County / regionCumbria
Turbines5
Installed capacity6.5 MW
Turbine capacity1.3 MW
Tip heightnot recorded
Operator (or applicant)Lambrigg Windfarm Ltd
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1997 1998 1999 2000 2001 2002 Project timeline Application submitted June 1998 Permission granted July 1999 Operational September 2001

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3390.

What the register tells us

The application was determined in about 13 months. The scheme has been operating for about 25 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 1.3 MW per turbine on average.