Land approx 75m South of 141

8 turbines · operational · Co. Tyrone

Wind farm facts

StatusOperational
County / regionCo. Tyrone
Turbines8
Installed capacity20 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Private Developer
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Project timeline Application submitted February 2005 Permission granted April 2005 Operational July 2007 Permission expired April 2013

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3251.

What the register tells us

The application was determined in about 2 months. A planning permission on this site expired in April 2013. The scheme has been operating for about 19 years. That works out at 2.5 MW per turbine on average.

Nearby

See all wind farms in Co. Tyrone.