Land at Overside and Greenwellheads Farms

4 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines4
Installed capacity9.2 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Greenside Wind Energy Ltd
Turbine manufacturerEnercon
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 Project timeline Application submitted March 2011 Permission granted September 2011 Operational November 2013

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3802.

What the register tells us

The application was determined in about 6 months. The scheme has been operating for about 13 years. That works out at 2.3 MW per turbine on average.