Land near Ventonteague

1 turbines · revised · Cornwall

Wind farm facts

StatusRevised
County / regionCornwall
Turbines1
Installed capacity1.5 MW
Turbine capacity1.5 MW
Tip height99 m
Operator (or applicant)Cornwall Council
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2014 2015 2016 2017 2018 2019 2020 2021 2022 Original scheme Application submitted March 2015 Permission granted October 2015 Permission expired October 2018 Later scheme Application submitted October 2018 Permission granted December 2019 Operational July 2020 Permission expired December 2021

The register links a second scheme on this site (REPD ref 7588, Operational): 1 turbines · 99 m tip height · applicant Cornwall Council. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 5153.

What the register tells us

The application was determined in about 7 months. A planning permission on this site expired in October 2018. That works out at 1.5 MW per turbine on average.

Nearby

See all wind farms in Cornwall.