Langley Moor

4 turbines · operational · County Durham

Wind farm facts

StatusOperational
County / regionCounty Durham
Turbines4
Installed capacity8 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)EDF Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted January 2005 Permission granted June 2005 Operational August 2008 Permission expired June 2018

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3248.

What the register tells us

The application was determined in about 5 months. A planning permission on this site expired in June 2018. The scheme has been operating for about 18 years. That works out at 2 MW per turbine on average.