Lindhurst Wind Farm

5 turbines · operational · Nottinghamshire

Wind farm facts

StatusOperational
County / regionNottinghamshire
Turbines5
Installed capacity15 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Npower Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 Project timeline Application submitted June 2006 Permission granted September 2007 Under construction January 2010 Operational November 2010 Permission expired September 2011

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2938.

What the register tells us

The application was determined in about 15 months. Construction to first power took about 10 months. A planning permission on this site expired in September 2011. The scheme has been operating for about 16 years. That works out at 3 MW per turbine on average.