Lissett Airfield Wind Farm

12 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines12
Installed capacity30 MW
Turbine capacity2.5 MW
Tip heightnot recorded
Operator (or applicant)Novera Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Original scheme Application submitted July 2006 Permission granted February 2007 Operational February 2009 Permission expired February 2013 Later scheme Application submitted October 2013 Refused August 2015

From application to operation, this scheme took about 3 years.

The register links a second scheme on this site (REPD ref 4298, Appeal Withdrawn): 5 turbines · 2.5 MW each · applicant Energiekontor UK. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3539.

What the register tells us

The application was determined in about 7 months. A planning permission on this site expired in February 2013. The scheme has been operating for about 17 years. That works out at 2.5 MW per turbine on average.

Nearby

See all wind farms in Humberside.