2 turbines · operational · Essex
| Status | Operational |
|---|---|
| County / region | Essex |
| Turbines | 2 |
| Installed capacity | 1 MW |
| Turbine capacity | 0.5 MW |
| Tip height | 77 m |
| Operator (or applicant) | Constantine Wind Energy |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 3 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3437.
The application was determined in about 18 months. Construction to first power took about 2 months. A planning permission on this site expired in May 2018. The scheme has been operating for about 10 years. That works out at 0.5 MW per turbine on average.