Little Byth

3 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines3
Installed capacity4.5 MW
Turbine capacity1.5 MW
Tip heightnot recorded
Operator (or applicant)Lovie Ltd
Turbine manufacturerEnercon
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted April 2009 Permission granted December 2009 Operational December 2012 Permission expired December 2018

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3722.

What the register tells us

The application was determined in about 8 months. A planning permission on this site expired in December 2018. The scheme has been operating for about 14 years. That works out at 1.5 MW per turbine on average.