26 turbines · operational · Kent
| Status | Operational |
|---|---|
| County / region | Kent |
| Turbines | 26 |
| Installed capacity | 59.8 MW |
| Turbine capacity | 2.3 MW |
| Tip height | not recorded |
| Operator (or applicant) | RWE npower |
| Turbine manufacturer | Nordex |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 7 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3096.
The application was determined in about 35 months. Construction to first power took about 11 months. The register records a refusal in October 2005 before the scheme progressed. Permission was ultimately granted on appeal in October 2005. A planning permission on this site expired in October 2018. The scheme has been operating for about 17 years. That works out at 2.3 MW per turbine on average.