11 turbines · operational · Dyfed
| Status | Operational |
|---|---|
| County / region | Dyfed |
| Turbines | 11 |
| Installed capacity | 9.4 MW |
| Turbine capacity | 0.85 MW |
| Tip height | not recorded |
| Operator (or applicant) | Westbury Windfarms |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 3 years.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3229.
The application was determined in about 15 months. A planning permission on this site expired in March 2011. The scheme has been operating for about 22 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 0.85 MW per turbine on average.