Lochend Wind Farm

4 turbines · operational · Highland

Wind farm facts

StatusOperational
County / regionHighland
Turbines4
Installed capacity9.2 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Wind Harvest
Turbine manufacturerEnercon
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted July 2013 Refused March 2014 Permission granted December 2014 Granted on appeal December 2014 Under construction May 2016 Operational May 2017 Permission expired December 2017

From application to operation, this scheme took about 4 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4299.

What the register tells us

The application was determined in about 17 months. Construction to first power took about 12 months. The register records a refusal in March 2014 before the scheme progressed. Permission was ultimately granted on appeal in December 2014. A planning permission on this site expired in December 2017. The scheme has been operating for about 9 years. That works out at 2.3 MW per turbine on average.