Lodge Farm 1

1 turbines · operational · Dyfed

Wind farm facts

StatusOperational
County / regionDyfed
Turbines1
Installed capacity1 MW
Turbine capacity1 MW
Tip heightnot recorded
Operator (or applicant)Private Developer
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted January 2005 Permission granted October 2005 Operational August 2006 Permission expired October 2017

From application to operation, this scheme took about 1 year.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3272.

What the register tells us

The application was determined in about 9 months. A planning permission on this site expired in October 2017. The scheme has been operating for about 20 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 1 MW per turbine on average.