Longlands Lane

1 turbines · operational · Gwent

Wind farm facts

StatusOperational
County / regionGwent
Turbines1
Installed capacity1.5 MW
Turbine capacity1.5 MW
Tip heightnot recorded
Operator (or applicant)Renewable Energy Systems (RES)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 Project timeline Permission expired November 2011 Application submitted October 2012 Permission granted November 2013 Under construction September 2014 Operational December 2014

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4196.

What the register tells us

The application was determined in about 13 months. Construction to first power took about 3 months. A planning permission on this site expired in November 2011. The scheme has been operating for about 12 years. That works out at 1.5 MW per turbine on average.