Loscar Farm

3 turbines · operational · South Yorkshire

Wind farm facts

StatusOperational
County / regionSouth Yorkshire
Turbines3
Installed capacity4.5 MW
Turbine capacity1.3 MW
Tip heightnot recorded
Operator (or applicant)REG Windpower (previously Cornwall Light and Power)
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 Project timeline Permission expired March 2000 Application submitted November 2004 Permission granted March 2008 Under construction January 2010 Operational January 2011

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3247.

What the register tells us

The application was determined in about 40 months. Construction to first power took about 12 months. A planning permission on this site expired in March 2000. The scheme has been operating for about 15 years. That works out at 1.5 MW per turbine on average.