Wind farm facts

StatusRevised
County / regionHighland
Turbines1
Installed capacity1 MW
Turbine capacity1 MW
Tip height80 m
Operator (or applicant)Ventus Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 Original scheme Application submitted June 2015 Refused January 2016 Later scheme Application submitted July 2020 Permission granted October 2020 Operational June 2021 Permission expired October 2023

The register links a second scheme on this site (REPD ref 8046, Operational): 3 turbines · 35 m tip height · applicant Ventus Renewables. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 5454.

What the register tells us

The register records a refusal in January 2016 before the scheme progressed. That works out at 1 MW per turbine on average.