Lower Tregeen, Davidstow - Wind Turbine

1 turbines · under construction · Cornwall

Wind farm facts

StatusUnder Construction
County / regionCornwall
Turbines1
Installed capacity0.9 MW
Turbine capacitynot recorded
Tip height77 m
Operator (or applicant)Powerquinn Limited
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2017 2018 2019 2020 2021 2022 2023 Project timeline Application submitted November 2018 Permission granted March 2019 Under construction July 2022 Permission expired September 2022

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 6818.

What the register tells us

The application was determined in about 4 months. A planning permission on this site expired in September 2022. That works out at 0.9 MW per turbine on average.