Lynemouth Windfarm (Resubmission)

13 turbines · operational · Northumberland

Wind farm facts

StatusOperational
County / regionNorthumberland
Turbines13
Installed capacity26 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Scottish Power Renewables
Turbine manufacturerproven
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 Project timeline Application submitted November 2006 Refused May 2007 Permission granted January 2009 Granted on appeal January 2009 Under construction July 2010 Operational April 2012

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3752.

What the register tells us

The application was determined in about 26 months. Construction to first power took about 21 months. The register records a refusal in May 2007 before the scheme progressed. Permission was ultimately granted on appeal in January 2009. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.