M1 J18 Wind Turbines

2 turbines · operational · Northamptonshire

Wind farm facts

StatusOperational
County / regionNorthamptonshire
Turbines2
Installed capacity4 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Airvolution Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Project timeline Application submitted September 2011 Permission granted February 2013 Under construction July 2014 Operational December 2014 Permission expired February 2019

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4598.

What the register tells us

The application was determined in about 17 months. Construction to first power took about 5 months. A planning permission on this site expired in February 2019. The scheme has been operating for about 12 years. That works out at 2 MW per turbine on average.