13 turbines · operational · West Glamorgan
| Status | Operational |
|---|---|
| County / region | West Glamorgan |
| Turbines | 13 |
| Installed capacity | 26 MW |
| Turbine capacity | 2 MW |
| Tip height | not recorded |
| Operator (or applicant) | Pennant Wind Energy Ventures |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 5 years.
The register links a second scheme on this site (REPD ref 4485, Operational): 1 turbines · 2.5 MW each · applicant Pennant Walters (MAESX) Limited. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2674.
The application was determined in about 31 months. Construction to first power took about 9 months. A planning permission on this site expired in May 2012. The scheme has been operating for about 15 years. That works out at 2 MW per turbine on average.