Magherafelt

1 turbines · operational · Co. Derry / Londonderry

Wind farm facts

StatusOperational
County / regionCo. Derry / Londonderry
Turbines1
Installed capacity1 MW
Turbine capacity1 MW
Tip heightnot recorded
Operator (or applicant)Tobermore Concrete Products
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2008 2009 2010 2011 2012 2013 2014 2015 2016 Project timeline Application submitted July 2009 Permission granted November 2010 Operational June 2015 Permission expired November 2015 Under construction November 2015

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3678.

What the register tells us

The application was determined in about 16 months. A planning permission on this site expired in November 2015. The scheme has been operating for about 11 years. That works out at 1 MW per turbine on average.

Nearby

See all wind farms in Co. Derry / Londonderry.