Mains of Hatton

3 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines3
Installed capacity2.4 MW
Turbine capacity0.8 MW
Tip heightnot recorded
Operator (or applicant)Eco2 /GreenCAT
Turbine manufacturerEnercon
Turbine modelE48

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Project timeline Application submitted November 2006 Permission granted September 2007 Under construction November 2011 Operational March 2012 Permission expired September 2016

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3980.

What the register tells us

The application was determined in about 10 months. Construction to first power took about 4 months. A planning permission on this site expired in September 2016. The scheme has been operating for about 14 years. That works out at 0.8 MW per turbine on average.