MARCH SEWAGE TREATMENT WORKS - WIND TURBINE

1 turbines · operational · Cambridgeshire

Wind farm facts

StatusOperational
County / regionCambridgeshire
Turbines1
Installed capacity2 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)TCI Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 Project timeline Application submitted July 2007 Refused May 2008 Permission granted February 2009 Granted on appeal February 2009 Under construction June 2012 Operational September 2012 Permission expired February 2018

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 2875.

What the register tells us

The application was determined in about 19 months. Construction to first power took about 3 months. The register records a refusal in May 2008 before the scheme progressed. Permission was ultimately granted on appeal in February 2009. A planning permission on this site expired in February 2018. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.