Mark Hill

24 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines24
Installed capacity56 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Force 9 Energy
Turbine manufacturerSiemens Gamesa
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 Project timeline Application submitted August 2005 Permission granted June 2008 Under construction October 2009 Operational June 2011

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3260.

What the register tells us

The application was determined in about 34 months. Construction to first power took about 20 months. The scheme has been operating for about 15 years. That works out at 2.33 MW per turbine on average.