Marr Windfarm

4 turbines · operational · South Yorkshire

Wind farm facts

StatusOperational
County / regionSouth Yorkshire
Turbines4
Installed capacity8 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Banks Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2005 2006 2007 2008 2009 2010 2011 2012 2013 Project timeline Application submitted December 2006 Permission granted July 2007 Permission expired July 2010 Under construction March 2011 Operational January 2012

From application to operation, this scheme took about 6 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3963.

What the register tells us

The application was determined in about 7 months. Construction to first power took about 10 months. A planning permission on this site expired in July 2010. The scheme has been operating for about 14 years. That works out at 2 MW per turbine on average.