Mawdesley Moss

3 turbines · operational · Lancashire

Wind farm facts

StatusOperational
County / regionLancashire
Turbines3
Installed capacity2.3 MW
Turbine capacity0.75 MW
Tip heightnot recorded
Operator (or applicant)Private Developer
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2006 2007 2008 2009 2010 2011 2012 2013 Project timeline Application submitted May 2007 Permission granted September 2007 Permission expired September 2011 Under construction April 2012 Operational August 2012

From application to operation, this scheme took about 5 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3944.

What the register tells us

The application was determined in about 4 months. Construction to first power took about 4 months. A planning permission on this site expired in September 2011. The scheme has been operating for about 14 years. That works out at 0.77 MW per turbine on average.