14 turbines · revised · Grampian
| Status | Revised |
|---|---|
| County / region | Grampian |
| Turbines | 14 |
| Installed capacity | 14 MW |
| Turbine capacity | 1 MW |
| Tip height | not recorded |
| Operator (or applicant) | Renewable Energy Systems (RES) |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
The register links a second scheme on this site (REPD ref 4109, Operational): 12 turbines · 0.85 MW each · applicant The Renewables Infrastructure Group (TRIG). Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3573.
The register records a refusal in December 2001 before the scheme progressed. That works out at 1 MW per turbine on average.
See all wind farms in Grampian.