2 turbines · operational · Humberside
| Status | Operational |
|---|---|
| County / region | Humberside |
| Turbines | 2 |
| Installed capacity | 5 MW |
| Turbine capacity | 2.5 MW |
| Tip height | 119 m |
| Operator (or applicant) | Seneca Global Energy |
| Turbine manufacturer | not recorded |
| Turbine model | not recorded |
Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.
From application to operation, this scheme took about 4 years.
The register links a second scheme on this site (REPD ref 4549, Revised): 3 turbines · 2.3 MW each · 119 m tip height · applicant Seneca Global Energy. Two schemes on one site usually mean a repowering or an extension — to be confirmed with the operator.
Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 3645.
The application was determined in about 6 months. A planning permission on this site expired in December 2015. The scheme has been operating for about 9 years. That works out at 2.5 MW per turbine on average.
See all wind farms in Humberside.