Melton Waste Park

2 turbines · operational · Humberside

Wind farm facts

StatusOperational
County / regionHumberside
Turbines2
Installed capacity5 MW
Turbine capacity2.5 MW
Tip height117 m
Operator (or applicant)Seneca Global Energy
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2014 2015 2016 2017 2018 2019 Project timeline Application submitted February 2015 Permission granted April 2015 Under construction June 2016 Operational March 2017 Permission expired April 2018

From application to operation, this scheme took about 2 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4995.

What the register tells us

The application was determined in about 2 months. Construction to first power took about 9 months. A planning permission on this site expired in April 2018. The scheme has been operating for about 9 years. That works out at 2.5 MW per turbine on average.