Michelin Tyre Co Ltd - Dundee

2 turbines · operational · Tayside

Wind farm facts

StatusOperational
County / regionTayside
Turbines2
Installed capacity4 MW
Turbine capacity2 MW
Tip heightnot recorded
Operator (or applicant)Ecotricity
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 Project timeline Application submitted May 2003 Permission granted September 2004 Operational May 2006 Permission expired September 2010

From application to operation, this scheme took about 3 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4681.

What the register tells us

The application was determined in about 16 months. A planning permission on this site expired in September 2010. The scheme has been operating for about 20 years. At that age, wind farms commonly become candidates for repowering or life extension — nothing in the register confirms such a plan here. That works out at 2 MW per turbine on average.