Mid Hill - Phase II

8 turbines · operational · Grampian

Wind farm facts

StatusOperational
County / regionGrampian
Turbines8
Installed capacity18.4 MW
Turbine capacity2.3 MW
Tip heightnot recorded
Operator (or applicant)Fred Olsen Renewables
Turbine manufacturerSiemens Gamesa
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 Project timeline Application submitted February 2003 Permission granted June 2005 Permission expired June 2011 Under construction August 2014 Operational December 2014

From application to operation, this scheme took about 11 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4627.

What the register tells us

The application was determined in about 28 months. Construction to first power took about 4 months. A planning permission on this site expired in June 2011. The scheme has been operating for about 12 years. That works out at 2.3 MW per turbine on average.