Middle Muir Wind Farm

15 turbines · operational · Strathclyde

Wind farm facts

StatusOperational
County / regionStrathclyde
Turbines15
Installed capacity51 MW
Turbine capacity3.4 MW
Tip heightnot recorded
Operator (or applicant)Banks Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 Project timeline Application submitted February 2012 Permission granted September 2014 Permission expired September 2015 Under construction January 2017 Operational May 2019

From application to operation, this scheme took about 7 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4440.

What the register tells us

The application was determined in about 31 months. Construction to first power took about 28 months. A planning permission on this site expired in September 2015. The scheme has been operating for about 7 years. That works out at 3.4 MW per turbine on average.