Middlemoor

18 turbines · operational · Northumberland

Wind farm facts

StatusOperational
County / regionNorthumberland
Turbines18
Installed capacity54 MW
Turbine capacity3 MW
Tip heightnot recorded
Operator (or applicant)Npower Renewables
Turbine manufacturernot recorded
Turbine modelnot recorded

♻️ Project timeline

Dated milestones from the UK Renewable Energy Planning Database (REPD), Q2 2026 — not estimates.

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Project timeline Application submitted December 2005 Permission granted August 2008 Under construction March 2012 Operational September 2013 Permission expired August 2017

From application to operation, this scheme took about 8 years.

Source: Renewable Energy Planning Database, Department for Energy Security and Net Zero, Open Government Licence v3.0. REPD ref 4019.

What the register tells us

The application was determined in about 32 months. Construction to first power took about 18 months. A planning permission on this site expired in August 2017. The scheme has been operating for about 13 years. That works out at 3 MW per turbine on average.

Nearby

See all wind farms in Northumberland.